New Hospital Updates
January Community Update
We are excited to share the ongoing progress of our new hospital construction. The structural steel work is now complete. Currently, over 50 tradesmen are onsite, diligently working on electrical, HVAC, sprinker systems, and framing. The interior priority wall framing in Area A is finished and has begun in Area B. Upcoming Construction Activities: What…
Read MoreDecember Community Update
The construction of our new facility continues, with significant advancements over the past month. The increased structural steel has shaped the building’s framework, paving the way for the next stages of construction. What’s Next in the Upcoming Weeks? Each phase brings us closer to the completion of a state-of-the-art healthcare facility that will serve our…
Read MoreNovember Community Update
Construction on the new hospital is advancing steadily, even with the welcome addition of much-needed rain. The project is on track as contractors continue to place the precast concrete wall panels, a major milestone in the construction process. After Thanksgiving, the structural steel contractors will be on-site to begin steel erection, marking another exciting phase…
Read MoreOctober Community Update
Exciting developments are underway at the new hospital construction site! The concrete pre-cast walls are now being installed, with eight to ten panels going up each day. It’s an impressive sight and a major step toward completing the new facility. Structural steel contractors will begin their work in the next two weeks, marketing another key…
Read MoreContractor for New Hospital Project Rebrands to Cerris
Harrison County Community Hospital’s new hospital project contractor, MW Builders, has rebranded as Cerris Builders. The name change is part of a larger initiative by parent company MMC Corp, which has united its various brands under the new name Cerris. The change was effective June 27, 2024. MMC Corp, new Cerris, brings nearly a century…
Read MoreSeptember Community Update
We are pleased to provide the latest update on the ongoing construction of our new hospital facility. The storm (Line 3) piping, structures, and lifeline installation for the east parking lot are expected to be completed this week. The east fire loop has already been successfully installed, and we are now preparing to install the…
Read MoreAugust Community Update
We are excited to share that the building footings, storm drainage, and underground utilities are underway. In addition, we successfully passed a surprise DNR inspection for the stormwater drainage. 4-Week Look-ahead: We are pleased to report that we remain scheduled for completion in April 2026.
Read MoreNew 39th Street Opens for Traffic, Focus Shifts to Parking Areas
As of Tuesday, June 25, the newly constructed 39th Street is officially open for traffic, marking a significant milestone in the ongoing infrastructure project. The project’s next phase will concentrate on developing the parking areas west of the new road. This includes installing underground utilities, curbing, and preparing parking lot surfaces. Once completed, the parking…
Read MoreJune Community Update
Pivotal stages of construction are currently underway for the new Harrison County Community Hospital facility. Key developments include: Looking ahead: HCCH extends our gratitude to residents for their cooperation and patience during this transformative phase. The new hospital promises to significantly enhance healthcare services for Bethany and surrounding communities.
Read MoreMay Community Update
The weather has posed a challenge for the new hospital’s construction progress this month. As of today, there have been a total of 17 weather days. However, the project remains on schedule. The storm drains for the new 39th Street have been installed, and concrete curbs will be set up in the next few weeks.…
Read More